L5 · Integrated systems testing

Level 5 Integrated Systems Testing — Whole Facility

Prove the building works as one system: cooling, power, controls, plumbing, fire protection, security and communications respond together, correctly, under every condition the facility will face.

Job-specific checklist 44 checks 8 tied to a source document3 tied to an RFI, Issue or Submittal

Scenario 1 — Normal Operations Baseline12 checks

BAS/EPMS: every controller communicating; status, metering and alarms correct; trending, schedules, remote access and graphics live
Data Hall DEC units respond to BAS; supply air, humidity, fan modulation, filter DP and water flow controlled; integrated with EPMS
Spec: 25 95 01
MDF DEC staging and lead/lag; packaged DEC units in electrical rooms; mini-splits on schedule and setback
Spec: 25 95 02 / 25 95 04 / 23 81 26
All 90 ridge dampers modulate on pressure/temperature with position feedback, coordinated with DEC units
Building static pressure control coordinates supply and exhaust and responds to door openings
EPMS monitors every main breaker; three-phase balance; power quality; dual source to DCB2 and the second RDS breaker verified
UPS under normal load with battery monitoring, bypass and EPMS alarms; lighting controls (occupancy, schedule, emergency transfer) integrated with BAS
Domestic water booster pumps, process water meter, pressure control and lead/lag; sanitary systems operational
RFI #67: Process water meter
Wet and preaction sprinkler supervision, fire pump and jockey pump, full fire alarm and VESDA operation with monitoring-station transmission
Cellular DAS and public-safety ERRCS coverage; 10-ft separation from WAPs; rack DAS power; BBU backup
RFI #84, #85
Access control and CCTV integrated, with event-triggered recording; structured cabling labeled per FDM
Spec: 28 10 00 / 28 20 00
Integrated automation network segmentation, firewall rules and redundancy; SCADA trending, reports and user levels; instrumentation accuracy
Spec: 25 15 40 / 25 15 50 / 25 35 00

Scenario 2 — Peak Load Conditions3 checks

Simulated maximum data hall heat load: all DEC units stage on, supply air held, electrical demand within design, no nuisance alarms
Simulated maximum electrical demand: distribution balanced, no overloads, metering accurate, power quality acceptable, cooling responds
Every system at peak simultaneously — HVAC, lighting, IT load — stable, no cascade failures, operators keep full control

Scenario 3 — Equipment Failure & Failover9 checks

Single DEC unit failure: remaining units compensate, space stays in limits, alarm and notification correct
Multiple DEC failures: alarm escalation and emergency response protocols activate
Ridge damper stuck open and stuck closed; supply and exhaust fan failures — response and pressure impact verified
Loss of primary utility feed: UPS carries critical load, load shedding and ATS operate, EPMS stays up on backup
Loss of secondary feed, UPS bypass/failure and branch breaker trips — isolation and alarms verified
BAS controller failure: equipment fails safe, backup takes over, manual override works
Network loss: local controllers keep running, recover cleanly; EPMS server loss: data buffered and resynchronized
Sensor failures produce alarm, default value or safe mode as designed
Lead booster pump failure starts lag pump; low water pressure; fire pump controller fault; sprinkler supervision loss — all alarm correctly

Scenario 4 — Fire Alarm & Life Safety Events6 checks

Data hall smoke detector: panel alarms, notification activates, signal transmitted to monitoring station
HVAC response: DEC units shut down per sequence, dampers close, exhaust runs per smoke control, ridge dampers go to fire mode
Spec: 25 95 01
Electrical response: non-essential loads shed, emergency lighting on, critical systems stay up
Access control response: doors unlock, hold-opens release, egress paths stay clear
Electrical room and office alarms: correct zone, local HVAC shutdown, egress lighting, elevator recall
VESDA Alert-level pre-alarm and escalation; manual pull station; sprinkler waterflow; fire pump automatic start on low pressure — each with EPMS visibility

Scenario 5 — Emergency Shutdown3 checks

Data hall EPO: correct shutdown sequence, electrical isolation, alarms, EPMS event capture, and correctly sequenced restart
Emergency HVAC shutdown: all equipment stops, dampers fail safe, manual restart verified
Full building evacuation: fire alarm, life safety, door release, emergency lighting, HVAC emergency sequence and emergency communications together

Scenario 6 — Operational Mode Transitions3 checks

Occupied ↔ unoccupied transitions: setpoints, lighting, HVAC setback, ventilation and pre-occupancy recovery
Maintenance mode: alarms suppress appropriately, other systems compensate, alarms restore on return
Manual override: indicated in EPMS, time-based release, manual return to auto

Scenario 7 — Monitoring, Alarming & Operator Interface4 checks

Critical, high, medium and low alarm priorities categorized, notified, escalated and acknowledged correctly
Trending, historical retrieval, export and storage capacity verified; automated energy, runtime and alarm reports
Graphics, navigation and control from graphics; user access levels, audit trail, password policy and session timeout
Secure remote and mobile access with full functionality and alarm notifications

Post-L5 Completion4 checks

Final L5 report; deficiencies resolved; as-builts, O&M manuals with actual performance data, warranty and systems operations guide
Recorded hands-on operator training: normal ops, alarm response, overrides, emergency shutdown, troubleshooting — with knowledge checks and sign-offs
Results presented to Owner and Commissioning Agent; third-party QA/QC sign-off; final acceptance signatures; documentation transferred
Site-specific gates: FDM log finalized (Issue #238); all SOO specs issued (RFI #44); DAS/ERRCS separation verified (RFIs #82, #83, #85); MSG-Alpha breaker work complete; all OFCI vendors on call
Issue #238RFI #44

Work sample — owner names removed. Site tags, RFI, Issue and Submittal numbers retained to show traceability. Tick boxes are for demonstration and are not saved.