Leading quality on one site while supporting two more in other states
A Director of Quality can't be on every site. What scales is a system: standard checklists that adapt to each job, one person in the field per site, and a daily rhythm that keeps every open item owned and dated. This is what that looked like in 2026.
Hyperscale data center campus — Central Texas
One of four data centers on a $1.2B, 7.55M sq ft campus. Third-party QA/QC for the general contractor.
- Led the site quality team and pre-energization inspections: SF6 MV switchgear, power skids, transformers, switchboards, VESDA
- Built the L2–L5 checklist program shown on this site
- Hired, onboarded and trained inspectors; ran a surge crew at peak
- Closed every finding from a GC documentation audit the same day
Data center project — North Dakota
Supported from Texas while leading the Texas site.
- Built the Control Power and Power Skid pre-energization checklists for the North Dakota team
- Wrote them as reusable templates — the site team adds its own drawings, submittals and MOP
- Standalone control power hold point before any medium-voltage energization
Data center Phase 1 — South Carolina
One QA/QC rep on site; quality managed remotely from Texas.
- Wrote the overall plan to energization and LV final inspection — critical path, QC requirements, RFIs, materials
- Wrote the two-week look-ahead used to run the weekly meeting
- Found staffing gaps and tracker errors that put the schedule at risk
How a remote site stays under control
From the South Carolina plan — the same rhythm works for any number of sites.
Division of labor
The person on site spends their time in the field: verifying fixes, witnessing torque, walking FOD, signing off observations. Everything that can be done from a desk — the open-items list, RFI and submittal follow-up, deliveries, status writing — is handled remotely.
Quality bar vs. contractor's call
The plans separate QC requirements (from specs, NEC and manufacturer instructions — not optional) from PM recommendations (staffing and sequence — the contractor's call). Firm on the standard, a partner on the means.
The two South Carolina plans, in full
Company, project and location names redacted. Both were written from the contractor's completion plan, tracker and field notes.
Path to House energization and LV final inspection
48-hour critical path with 15 energization-stopper items, two-week look-ahead, ten QC requirements tied to 47 open observations, PM recommendations, 20 clarification questions, and the open RFI, materials and tracker-error lists.
Read the overall plan → Two-week look-aheadTwo-week game plan for the weekly meeting
The short version: six things this week, six next week, everything else parked and tracked remotely — each with an owner and a "done when."
Read the two-week plan →