The short version for the weekly meeting: six things this week, six next week, everything else parked and tracked remotely.

From Daniel Dible — Quality Manager, QA/QC firm
To QA/QC representative (on site); electrical contractor point of contact
Subject Data Center Phase 1 — Two-week game plan for today's meeting (7/14 – 7/28)

Here's the short version for today's meeting. Two goals for the next two weeks: energize the House clean on Friday 7/17, then get the LV punch work staffed and moving so the 8/10 final inspection is real. Six things this week, six next week. Everything else is parked, and I'm tracking it from Texas. The full plan with owners and open questions went out earlier today.

Key dates: 7/14 fuel delivery and L2 inspections start · 7/16 final inspection and third-party FOD · 7/17 House energization · 7/21–22 lighting controls start-up · 7/26 busway witness (confirm vs. 7/16) · 7/28 Data Hall due · 8/10 LV final inspection · 8/28 LV energization

How we'll work it

The contractor's crews do the work. The on-site rep verifies it in the field and signs it off. I keep the list, follow up on RFIs and deliveries, and send status Tuesday and Friday. The contractor PM is our single point of contact — one owner and one date per item. The quality bar doesn't move; staffing and sequence are the contractor's call.

  • Every morning, 15 minutes, remote lead and on-site rep: what got verified yesterday, what's being verified today, what's stuck.
  • Every day, on-site rep and PM walk the day's close-outs. Printed observation sheets are signed and closed in Procore the same day.
  • Tuesday and Friday: written status — open items, dates, blockers.
  • An item is closed when the fix has been seen in the field — not when the tracker says 100%.

This week: 7/14 – 7/19 — House energized Friday 7/17

Shaded items can stop energization by themselves, so they go first.

#WhatDone when
1Close the stoppers: OBS #146 disconnected control wire; HP-4E-1 Section 1–2 jumper rating and panel schedules (OBS #135); HATS-OS-1 neutral/ground RFI.Fixed or answered and verified before Thursday's final inspection.
2Generator: finish control wiring, confirm the retorque, covers on. Fuel delivery today.Torque record and covers checked.
3Labels: the corrected label, device plates, transformer phenolics, then a final label walk.OBS #88 and #89 closed for the House.
4Disconnects 00/01DISC01–02-N (re-pull, re-torque, FOD) and the MPOE-2 room (torque and QC every panel and the tap box).Both walked.
5Fire alarm: the FA sub's OK in writing on generator devices; the AHJ's answer on FA panels on temporary power.Both in writing.
6Re-check the 12 items marked Pass whose notes say they aren't done.Each confirmed or reopened before FOD.

Also this week: HP-4E-1 CTs (keep a tech ready for same-day install) · UL Bakelite sign-off · mechanical pre-start-up checklists · municipal inspection results · busway snap-test prep: settle 7/16 vs. 7/26 and check wall plates and penetrations on the busway route.

Next week: 7/20 – 7/28 — LV punch staffed, Data Hall done 7/28

Day shift drops from 53 to 33 on 7/20, and the plan has crews on only 3 of the 47 open LV observations and 9 of the 68 open equipment items in Reserve, Phase 1 and Mechanical. Fixing that is the whole week.

#WhatDone when
1Staff the LV punch work: a dedicated torque-and-close-out crew from 7/20, with these items added to the manpower plan.Crew named and in the manpower plan.
2Work upstream to downstream — switchboards, UPS, STS and PDUs, then panels, transformers and mechanical. Verified behind the crew the same day.Observations closing every day.
3Stop repeats: calibrated wrench and a torque sheet per piece of gear; crimp tool and die check plus a first-crimp check each shift; vacuum before close-up.Sheets spot-checked.
4Busway: finish the torque before the snap-torque witness; Data Hall rail correction underway; rail-support RFI answered.Witness passes the first time.
5Data Hall by 7/28: ladder tray (60%), basket tray and fiber guide (80%), busway (40%), cord sets, lighting sensors, OBS #151 VESDA conduit.Ready for inspection.
6Put dates on the calendar: top-hat delivery for the UPS-to-battery pathway, the testing firm's IR scan of the House under load, and the load bank test.All three dated.

Parked — tracked from Texas, no field action this window

Vault lids, collars and manhole items · site cleanup and the quazite box (OBS #139–141, no energization impact) · fiber guide clamp alternative (EOR review first) · rental releases · structural review of strut supports (OBS #100, #130 — no new load on flagged supports until it's back) · lightning protection UL certification (due 7/31) · change orders (compressor, load bank, UPS cable) · tracker cleanup (night-shift formula, items closed at 0%).

Three asks for today

  1. Put one name on every item above.
  2. Confirm or reset three dates: cable tray grounding (the Saturday target), the after-energization list (Sunday), and the busway snap test (7/16 or 7/26).
  3. Get the generator RFI narratives written, and add LV punch crews to the manpower plan.

The quality bar stays where it is: full torque marks, clean gear, right lugs. That's what protects the crews at energization. Everything else we work out together.

Daniel Dible
Quality Manager · QA/QC · Supporting the site remotely from Texas

Work sample — company, project and location names redacted for confidentiality.