L2 · Physical installation
Switchgear & Distribution L2 — Physical Installation Verification (Job-Specific)
Verify distribution gear matches approved submittals and every RFI resolution — especially where drawings and submittals disagree — before energization.
Medium-Voltage Switchgear (MVS-A / MVS-B)4 checks
MVS-A/B nomenclature on labels matches the approved configuration
RFI: MVS A/B Nomenclature Change — names swapped to prevent conduit crossing
WhyWrong labels mean wrong connections at energization
Surge arresters on the 35 kV overhead drops — not on MVS incoming feeds
RFI: RDS 35 kV Overhead Surge Arresters
WhyMissing overhead arresters means no surge protection
Underground conduit does not cross between MVS-A and MVS-B
RFI: MVS A/B Nomenclature Change
WhyCrossed conduit means incorrect install
Pad level within manufacturer tolerance; bolted connections torque-marked; grounding per 26 05 26
NETA ATS 7.5.4Spec 26 05 26
Why35 kV grounding is life-safety critical
RSB Panels at Modular Power Skids — Critical3 checks
RSB panel has FIVE 800 A sub-feed breakers — not four 800 A + one 400 A
RFI: RSB Panel Breaker Discrepancy — single-line vs approved submittal
WhyWrong breaker size is a coordination failure
No adjustable rating dip switch set to 400 A on any 800 A breaker
RFI: RSB Panel Breaker Discrepancy
WhyField must match the approved submittal
Panel secure and level on the skid; sub-feed terminations torqued with phase ID
WhyFive identical breakers raise mis-phasing risk
Transfer Switches (Spec 26 36 00)3 checks
Complies with NFPA 99, NFPA 110 and UL 1008
Spec: 26 36 00 / Submittal #148
WhyNon-compliant life-safety gear must be rejected
Manual transfer warning labels legible; annunciation and control wiring terminated
NETA ATS
WhyIncomplete circuits fail insulation testing
Interlocks free of shipping blocks and temporary restraints
Spec: 26 36 00
WhyForgotten blocks stop transfer
Equipment Rooms3 checks
Electrical gear in dedicated MEP rooms — not in equipment nooks
RFI: Site-Specific Adaptations and MEP Room Layout
WhyNooks must stay clear for DEC unit clearances
Walls added on east and west sides of nooks per Owner preference
RFI: Site-Specific Adaptations
WhySeparates wall-mounted gear from DEC units
Fire riser rooms (two, 500 SF) hold only fire-protection electrical gear
Fire marshal driven site adaptation
WhyCode separation
BMS Cable Lengths1 checks
Every run from electrical equipment to IDF racks below 90 m, with measured lengths documented
Issue #81: Constructability — BMS design lead concern
WhyVerification, not assumption, closes the issue
Switchboards & Panelboards4 checks
Digital multi-meters installed for ammeter, voltmeter and power metering
Spec requirement
WhyNo meters, no monitoring
Bus connections accessible for post-placement tightening; temporary lifting hardware removed
NEMA PB 2.1
WhyRigging hardware left in creates arc-flash hazards
Engraved nameplates and breaker directories installed
WhyNeeded for NETA testing
Panelboards: vault-type keyed-alike latches; breaker-type main; door swings 90° clear
NEMA PB 1
WhyNEC working space
Electric Door Hardware Coordination3 checks
Electric locks and door position switches at openings 003.A.26A, .29A, .31A, .34A per updated hardware sets
RFI: Door Hardware & Security Coordination
WhySchedule and security drawings conflicted
Opening 003.A.35A has electric lock and DPS added
RFI: Door Hardware & Security Coordination
WhyOriginal set I2R1 had no electric hardware
Opening 003.F.04A has DPS only — no electric lock
RFI: Door Hardware & Security Coordination
WhySecurity drawings govern
Grounding & Documentation2 checks
All gear grounded per 26 05 26; ground bars torqued and marked; EGCs sized for fault current
Spec: 26 05 26
WhyLoose grounds fail NETA testing
Factory torque documentation submitted; installed equipment matches approved submittals; nameplates match shop drawings
RFI: RSB Panel Breaker Discrepancy
WhySubmittals govern, not drawings
Common failures & lessons learned
- Testing prep: NETA ATS firm must be a NETA Full Member or OSHA-accredited; lead tech NETA or NICET certified.
- Key rule on this job: field installation must match the approved submittal — not necessarily the drawing.
Work sample — owner names removed. Site tags, RFI, Issue and Submittal numbers retained to show traceability. Tick boxes are for demonstration and are not saved.